システムコンポーネントがどこまでできているかは言わなかったが,
構造部分の 90% はできているとのこと.

最終組立てはこの秋に小牧工場で開始.
改訂後のスケジュールでは,エンジンの PW1200G は 2014 年の春に
三菱にデリバリーされるはず.

"Mitsubishi is now assembling its first flight test and ground test
aircraft. Though Fukuhara could not put a figure on the percentage of
system components that have been produced, he says that 90% of the
jet's structure has been manufactured. He also adds that no parts had
to be reproduced because of the ODA system.

Final assembly of the first MRJ test aircraft will start this autumn
at Mitsubishi Heavy Industries' Komaki plant in Nagoya. Under the
revised schedule, the first Pratt & Whitney PW1200G engines should be
delivered to Mitsubishi in the spring of 2014."